Top Special Offer! Check discount
Get 13% off your first order - useTopStart13discount code now!
Critical path refers to the activities sequence which determines the project duration. The time taken for a project to get to completion is determined by the longest tasks sequence of the activities. Thus, activities that lie on the critical path are the most important ones and need to be given more attention if the project is to be completed in the shortest time possible. A delay, however small, in an activity on the critical path leads to a delay in the overall project completion (Meyringer, 2006).
According to the activities breakdown above, the critical path is identified as: engineer inspection succeed by inspector approval and occupancy permit. That is to imply that engineer inspection and that of inspector approval and occupancy permit are two things which should be given the highest priority because a delay in any or both will delay overall project completion. The two activities take a total of 155 days, that is, 152 days for engineer inspection plus three days for inspector approval and occupancy.
Custom Spreadsheet
ID
Task
Duration (days)
Predecessor
Lag (days)
Start
Finish
1.11
Land acquisition contract signing
2
-
15/01/2018
17/01/2018
1.1.2
Project Plan review
1
1
18/01/2018
18/01/2018
1.1.3
Appoint Architect, incl. inspections
152
1
15/01/2018
16/06/2018
1.1.4
Apply for building permits
2
3
17/01/2018
19/01/2018
1.1.4
Site plan approval
3
3
17/01/2018
20/01/2018
1.1.5
Funding approval and release
1
2
18/01/2018
18/01/2018
1.1.4
Building permit approvals
1
4
19/01/2018
19/01/2018
1.3.1
Demolition of existing building
16
7
19/01/2018
4/2/2018
1.3.2
Excavate land
10
7
19/01/2018
29/01/2018
1.3.3
Lay foundations
14
9
29/01/2018
12/2/2018
1.3.4
Lay concrete
5
9
19/01/2018
24/01/2018
1.3.5
Install steel framework
21
11
2
26/01/2018
16/02/2018
1.3.6
Roof trusses installed
7
11
24/01/2018
31/01/2018
1.3.7
Plumbing installed
19
12
16/02/2018
7/3/2018
1.3.8
Brickwork laid
20
14
7/3/2018
27/03/2018
1.4.4
Surveyor inspection
1
-
17/05/2018
17/05/2018
1.4.1
Install interiors carpet, tiling
28
15
27/03/2018
24/04/2018
1.4.4
Engineer inspection
152
-
15/01/2018
16/06/2018
1.4.4
Director inspection
152
-
15/01/2018
16/06/2018
1.4.1
Finishes including lock up
25
17
24/04/2018
19/05/018
1.5.4
Inspector approval and occupancy permit
3
19
16/05/2018
19/05/2018
1.3.9
New building gazetted and commissioned
6
21
1
20/05/2018
25/05/2018
The Network Diagram
Reference
Meyringer, M. (2006). U.S. Patent No. 7,050,056. Washington, DC: U.S. Patent and Trademark Office
Hire one of our experts to create a completely original paper even in 3 hours!